NEBUTA NO IE WARASSE 091014

A 100 ton crane has been brought on site and in this image is assisting the installation of the reinforcement bars in the resaurant area.

Around the basement core a trench is still visible as works are still ongoing to remove the temporary retaining walls that kept the ground water out of the pit. As the concrete of the basement and the water barrier has been installed the removal of the barrier is undertaken before the connection between the L1 floor and the basement can be executed.

The basement nearing completion of the concrete walls.